Interstate 275 from U.S. 41 to north of the Pasco County Line (resurfacing, completed May 2003)
Project Description
Financial Project # 403740-1-52-01
Project Length: 6.8 miles
Construction Cost: $1.8 million
Contractor: APAC-Florida, Inc.
Start Date: February 9, 2003
Completed: May 5, 2003
About this Project
The Florida Department of Transportation has completed milling and resurfacing Interstate 275 from U.S. 41 to north of the Pasco County line. The project will allow the road surfaces to be functional until the widening project begins in that area in 2007.
Improvement highlights for this project included: