I-75 Bridge Deck Repair over the Alafia River (completed March 2016)

Project Description

Financial Project Number: 432271-1
Project Limits: I-75 northbound and southbound over the Alafia River
Project Length: One-quarter mile
Estimated Construction Cost: $378,109
Contractor: Bridge Masters Construction, LLC
Contract Start Date: February 6, 2016
Completion Date: March 3, 2016

About this Project
The Florida Department of Transportation's (FDOT) contractor repaired the bridge deck on the I-75 northbound and southbound bridges over the Alafia River (just north of Gibsonton Drive/Exit 250).

Traffic Flow
The construction phasing was designed so that all existing lanes of traffic remained open on I-75 during peak traffic hours and major special events.

Night Work
In order to maintain the construction schedule and to minimize the impact to the traveling public, lane closures were used during nighttime hours as needed.

Lane Closure Hours
7:30 p.m. to 6:30 a.m.