I-275 Bearings and Inspection on Sunshine Skyway Bridge (completed July 2013)
Project Description
Financial Project Number: 423480-1
Project Limits: Skyway Bridge
Project Length: 4.1 miles
Construction Cost: $2 million
Contractor: Quinn Construction, Inc.
Start Date: May 1, 2012
Completion Date: July 24, 2013
About this Project
The Florida Department of Transportation's contractor replaced bridge bearings, performed various maintenance work and inspected the Sunshine Skyway Bridge.