I-275 from 38th Ave. S. to 26th Ave. S. (guardrail - completed July 2008)
Project Description
Financial Project Number: 419202
Project Length: approximately 3/4 mile
Construction Cost: $455,000
Contractor: Highway Safety Devices
Start Date: June 2, 2008
Completed: July 30, 2008
About this Project
The Florida Department of Transportation's contractor installed new guardrail in the median, miscellaneous asphalt, and concrete gutter on I-275 from south of 38th Avenue South to 26th Avenue South.
Lane Closures
Lane closures hours were:
Southbound I-275: 7 a.m. to 4 p.m. and 8:30 p.m. to 6:30 a.m.
Northbound I-275: 8:00 p.m. to 6:00 a.m.
Ramp from westbound I-4 to southbound I-75 to be closed several nights
Posted 7/7/2017 8:00:00 AM
Night lane closures on the southbound Howard Frankland Bridge
Posted 7/7/2017
Night lane closures on southbound I-275 exit ramp to Busch Boulevard and on Busch Blvd.
Posted 7/7/2017
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.