I-275 Resurfacing from the Sunshine Skyway to the north toll plaza (completed September 2004)

Project Description

Financial Project # 406540-3-52-01
Project Length: 3.6 miles
Estimated Construction Cost: $2.25 million
Contractor: Ajax Paving Industries
Start Date: June 6, 2004
Completed: September 20, 2004

About this Project
The Florida Department of Transportation milled and resurfaced the northbound and southbound I-275 roadways beginning at the north end of the Sunshine Skyway Bridge to approximately 1/4 mile north of the north toll plaza. Additionally, the rest area parking lot, bicycle path, frontage roads, and fishing pier ramps were resurfaced. There were also sign and pavement marking upgrades and repairs made to guardrail.

Lane Closure Hours were
* 7:30 p.m. to 6:30 a.m. Sunday thru Thursday nights as needed.
*Public access was maintained to the fishing pier and rest area at all times during construction activities.

Improvement highlights for this project included:

  • Resurfaced the existing pavement as described above.
  • Upgraded pavement markings.