I-275 Resurfacing from the Sunshine Skyway to the north toll plaza (completed Spring 2004)
Project Description
Financial Project # 40654015201 & 40654025201
Project Length: 3.6 miles
Construction Cost: $2.95 million
Contractor: Ajax Paving Industries
Start Date: July 7, 2003
Completed: Spring 2004
About this Project
The Florida Department of Transportation's contractor, Ajax Paving Industries, will resurface the northbound and southbound I-275 roadways beginning at the north end of the Sunshine Skyway Bridge to approximately 1/4 mile north of the north toll plaza. Additionally, the rest area parking lot, bicycle path, frontage roads, and ramps will be resurfaced. The guardrail in the median will be upgraded to today's safety standards.
Lane closures will be allowed from 7:30 p.m. to 6:30 a.m. Sunday thru Thursday nights only. Public access will be maintained to the fishing pier and rest area at all times during construction activities.
Improvement highlights for this project include:
Contact Person(s)
Media Contact
Marian Scorza
(813) 975-6038
E-mail
I-275 lane closures on Skyway Bridge at night
Posted 5/24/2013
Night lane closures on I-4 between Exits 1 and 3
Posted 5/24/2013
Traffic detoured off eastbound Selmon Expressway at night
Posted 5/24/2013